|
A major silicon wafer
production plant in Silicon Valley, California managed to carry
on full 24 hour production whilst having seismic protection fitted
to it's production plant, which presented an enormous challenge
to the contractors.
It was decided to
protect the building from seismic activity by strengthening the
structure with external steel columns and shielding the building
by excavating underneath the foundations and installing base isolators.
Converting the existing footings into columns resting on the isolators
required filling the gap between the footings and the concrete
slabs and anchoring the rebar to the existing columns.
The problem seemed
impossible due to the difficulties of locating the rebar, however,
the problem was eventually solved by using the Borehole Probe
attachment to accurately locate the rebar so as not to cause any
damage. 21mm holes were drilled and the Borehole probe used to
'map' the rebar locations in all directions from the bore hole.
Once the rebar had been found, holes could then be safely drilled
to install epoxy dowels to bond the rebar to the columns.
Chuck Queen - Project
Manager for Nielsen Dillingham Builders Inc said:
"
Nielsen
Dillingham Builders Inc
Web-site
|