|
In an on-going programme
since 1993, hundreds of post-tensioned concrete bridges have been
earmarked for initial inspection and subsequent physical investigation.
Jack Barfoot reports from a typical example.
The Department of Transport
(now called the Highways Agency) made an Order for the special
inspection of certain post-tensioned concrete bridge decks and
substructures. This following a growing awareness of cases of
inadequate and incomplete internal grouting to tendon ducts in
prestressed post-tensioned decks. Leakage of moist air, water
or de-icing salts through the deck joints could consequently lead
to significant corrosion of the stressing tendons.
There are three stages
of investigation for each bridge involved. A Preliminary Desk
Study reviews documents to verify the bridge structure and indicate
possible vulnerable locations. A Preliminary Site Inspection then
provides a visual examination to identify distressed areas and
to plan an investigation programme. The Site Investigation itself
takes place after which the Project Manager reports on the structural
condition of the bridge and any future monitoring requirements.
Harlaxton Road Bridge
in Lincolnshire carries the A1 Grantham bypass over the Grantham-Melton
Mowbray (A607) road. It exemplifies what the inspections and investigations
entail and how modern cover meter and probe equipments reduce
on-site times and destructive drilling.
The bridge, built in
1961, is a simply supported three-span structure with a skew of
37 degrees. Each span consists of a 200mm thick reinforced concrete
slab supported by sixteen prestressed post-tensioned longitudinal
precast beams. The beams are connected transversely at each end
and at mid-span by reinforced concrete diaphragms. Two reinforced
concrete piled abutments and two piled portal piers of five arches
make up the substructure.
The Preliminary Site
Inspection produced no visual evidence of significant deterioration
to the post-tensioned beams in critical areas. However, indications
of water leakage at beam ends, over abutments and piers demonstrated
that there was a potential for reinforcement and prestressing
steel corrosion. It was recommended that site investigations should
be undertaken to assess the extent and severity of any deterioration.
Dr Donald Pearson-Kirk,
an Associate of multi-disciplinary consultants Parsons Brinckerhoff
Limited (formerly PB Kennedy and Donkin) was in charge of the
investigative work, carried out by two teams each of two men.
"What we are
particularly looking for are signs of deterioration and pitting
corrosion to the tendons, which would reduce their size and the
efficiency of the prestressing. Unlike general rusting of reinforcement,
which would lead to identifiable spalling of concrete, pitting
corrosion is not necessarily visible without physical investigation".
"The investigation
falls into two main parts. First of all use of cover meters to
locate the rebars to connect to take the half-cell potential measurements
to quantify electrical activity within the concrete, and importantly
obtain depths of cover measurements. Samples of concrete dust
are taken at different depths and sent to a laboratory together
with grout samples - to be tested for chloride ion content. Depth
of carbonation penetration is also determined".
"Then we carry
out actual exposures of the ducts and tendons to find any visual
evidence of deterioration in the duct, grout or tendon".
An important factor
in the investigation was the choice of equipments used, he pointed
out.
"We look for a
covermeter which not only gives accurate measurement of cover
but also provides a good estimate of bar size, easily and clearly
read in all light conditions. This is vital for examination with
minimal damage of those areas of a structure, particularly when
no drawings are available. Speed and accuracy in a cover meter
is economic because it cuts job time and vitally eliminates wrong-guessing.
For these reasons we go not just for requipment which is up-to-date,
but particularly seek an instrument which is at the cutting edge
of microprocessor technology. The covermeter is a primary tool
in bridge work - without it we would just be making time-wasting
break outs to get information".
The unit chosen for
the Harlaxton Road Bridge was Elcometer P330 Covermeter, which
exceeds both UK and European standards. Using pulse induction
technology, the instrument can give either continuous fast scanning
of bar sizes and cover or orthogonal precision measurement of
single bars. It also features four-button control and one-handed
operation where needed, combined with a back lit read-out and
audible signal.
A Protovale covermeter
used with an inductive probe enables ducts to be located and approached
safely. Out of place ducts, or ducts where no profile information
has been made available, may be safely found.
Remedial work will
call for voids within ducts to be properly regrouted and for exposed
tendons to be covered with a corrosion inhibiting coating. Exposed
surfaces of investigative holes in the concrete will be sealed
with a primer and made good with a proprietary repair mortar in
layers not to exceed 40mm.
Investigation of Harlaxton
Road Bridge was carried out for the Engineering Consultancy Services
of Lincolnshire County Council with P B Kennedy and Donkin, (now
Parsons Brinckerhoff Ltd) as engineering consultants.
Parsons
Brinckerhoff Ltd website
|